Sleepy Hollow |
Code of Ordinances |
Part II. General Legislation |
Chapter 190. Excavation, Filling and Topsoil Removal |
Article II. Excavation, Tree Removal or Topsoil Stripping Permits |
§ 190-9. Duration of permit.
Latest version.
-
Permits under this article shall be for a period of no longer than one year or such shorter period as may be prescribed by the Planning Board with a view to having substantially continuous operations in connection with the excavation covered by the permit, subject only to interruption of work caused by seasonal conditions, such permits to be subject to termination if work is interrupted for a period of more than 60 days due to causes other than the weather or other seasonal conditions. Where work under the initial or renewal permit issued under this chapter has been pursued with reasonable diligence, a renewal permit may be issued without a new application upon payment of a fee in an amount set by resolution of the Board of Trustees, provided that the required bond or cash deposit shall remain in force and that the other requirements in connection with the application are currently up to date.